Terang BESS

Fire systems supporting a 100 MW / 200 MWh energy storage facility.

Completed
Client
Location
Terang, Victoria
Industry
Battery Energy Storage Systems Fire Protection
System Used
Canadian Solar CE Battery Storage

The Terang Battery Energy Storage System is a 100 MW / 200 MWh facility beside the Terang Terminal Station in south west Victoria, comprising 48 battery containers across 1.4 hectares. DIS Fire Systems delivered the complete fire protection scope, covering design, supply, installation and commissioning, along with documentation to support CFA and local authority compliance.

The Challenge

Delivering a compliant multi-stage fire-protection package aligned with CFA-approved Fire Management Plan requirements.

The Terang BESS required complex integration between on-site infrastructure, switchroom detection systems, and containerised BESS panels. DIS Fire Systems managed phased delivery under tight regulatory timelines, coordinating with TEC-C, FRV and Canadian Solar to align with FMP. Challenges included synchronising the main FIP logic with multiple field loops, maintaining documentation traceability for CFA audit, and completing over 400 m of hydrant ring-main installation while other trades remained active on site

Our Approach

End-to-end design, installation & commissioning under a four-phase ITP program

DIS Fire Systems delivered the full lifecycle of fire-protection works for the Terang BESS, from concept design through to commissioning and documentation closeout. The process began with detailed design coordination covering hydrant coverage, hydraulic demand calculations, and pump sizing aligned with CFA and FRV requirements.

The Result

Comprehensive fire-system commissioning supporting project energisation.

The Terang BESS fire protection system was commissioned and accepted ahead of program. The final package spanned hydrants, tanks, pumps, detection systems and field networking. All documentation, including ITPs, ITRs, SAT records and Fire Management Plan linkage, was endorsed and submitted to the CFA as part of the final construction compliance process.